- 2021-08-11 05:52:57
- LAST MODIFIED: 2024-11-21 14:15:54
Much-hyped work on underground cabling in Dhanmondi set to start in Sept
Photo Collected :
UNB Dhaka: Aug-11
Dhaka Power
Distribution Company (DPDC) will start physical work on taking overhead cables
underground in the Dhanmondi area next month as part of its mega project to
ensure safer transmission of electricity.
“We’ve completed all
our necessary preparation at a meeting today (Tuesday) to start the job in
September”, said Bikash Dewan, managing director of the DPDC, a public limited
company under the Power Division of the Ministry of Power, Energy and Mineral
Resources.
He said the
distribution body is now waiting for the permission from Dhaka North City
Corporation (DSCC) to dig the streets in the Dhanmondi area where the project
will start on a pilot basis.
“We hope we’ll get the
permission soon as the DSCC mayor is very positive about our project,” he told
UNB.
The Dhanmondi
underground cabling project is part of the DPDC’s mega scheme for which the
organization signed a contract with the Chinese contractor TBEA in September in
2019.
Under the Dhanmondi
project, 190 km of overhead electricity cables, an eyesore in the city, will be
taken underground, DPDC officials said.
Of these, about 115 km
are of 11 kV overhead lines, and 75 km are 0.4 kV lines, they said adding that
all kinds of overhead electric cables will go underground and no cable will
remain visible in a particular part of Dhanmondi area that includes Satmasjid
Road, Mirpur Road, City College and Greenherald School area.
The DPDC officials said
the China-funded Tk20,500 crore worth mega scheme also includes setting up 40
substations in the city and moving overhead cables of Hatirjheel Lake
underground. Taking overhead cables underground from Jahangir gate in
Cantonment to Motijheel is also included in DPDC’s other similar project.
Earlier, DPDC completed
its design and plan to implement its proposed underground cabling project to
make the city free from overhead power cables.
“Already, some of the
equipment reached the country and some are on the way,” he said, adding that
pole-mounted transformers will be replaced with box-type transformers under the
project.
Some 36 box-type
transformers, 296 of 6-way ring main units (RMU), 34 of 3-way RMUs and 130 LV
Cabinet will be installed to facilitate the underground cabling system, Bikash
said.
DPDC officials said the
project was supposed to kick off in January last year. But the Chinese
engineers who were responsible for designing the works got stuck in their
hometown Wuhan following the outbreak of Covid-19 pandemic.
But they later returned
to Dhaka and got engaged in the project after the improvement in the
coronavirus situation both in China and Bangladesh.
Bikash said once the
project is implemented, it will play a vital role in improving the power
distribution system and substantially check the unexpected interruption in
power supply.
There are widespread
allegations from the consumers that interruptions take place frequently in many
areas in the city.
DPDC officials admitted
that it happens due to a weakness in the distribution system despite the fact
that there is no shortage in electricity supply.
Under the power
distribution system upgrading project, the capacity of a number of substations
will also be improved, they added.
Before starting the
fieldwork, DPDC has invited both city corporations, internet service providers
(ISPs) and cable TV operators to join the project for its proper implementation
through better coordination.
But the power
distribution company’s call seems to have gone unheeded as it has not yet
received any response from other authorities.
“So far, we’ve not
received any response to our appeal to the city corporations and others,” said
Bikash.
City’s overhead cables,
especially the internet and cable TV lines, have created a huge pressure on
electricity lines which often pose a serious threat to public safety.
The DPDC top executive
said the organization is now installing a 132/33 kV substation project at
Shahidulla Residential Hall area in Dhaka University to enhance its
distribution capacity for which some high-voltage cables are being laid
underground in the city Paltan area.
End/Dct/Unb/Sma/